HRB Emergency Repair (Reg 10)
For urgent works needed to make a higher-risk building (HRB) safe, secure or operational after an unexpected failure or incident. Work may start straight away when the statutory emergency criteria are met. You must then give notice to the Building Safety Regulator (BSR), describing the work and why it was urgent, as soon as reasonably practicable after it starts, and seek a regularisation certificate as soon as practicable after it is finished. Emergency works must not be used to avoid the normal approval process.
Where it is available: on a work record created from the building (not from a project), for an HRB building only.
The forms: the record works around the BSR's forms. ER01 is the Regulation 10 notification. ER02, the Client Signed Statement, is only needed when an agent acts for the client. ER03, the Regularisation Application (Regulation 47), is only needed when the works have already started. You enter the information once and the forms share it.
The pathway has 12 steps after the opening steps. You can move freely between them: nothing stops you from continuing, and whatever is still missing is listed at Package ready.
4. Client Assessment
Five questions that decide which forms the record needs.
- Have the works started? No, not yet (the notification goes in before work begins) or Yes, they have started. Yes makes the ER03 regularisation application required.
- Who is the Responsible Person? Choose I know who they are and give their name, organisation and email (phone is optional). They are accountable under the Building Safety Act and sign off ER01. If you don't know, Search the public register opens the Higher-Risk Buildings Register on gov.uk.
- Are you the Client, or an Agent acting for a Client? If you are an agent, give your organisation; the record then needs ER02, the Client Signed Statement.
- Describe the building safety risk that has been identified, and why immediate action is needed.
- Reasonable steps to manage the risk: what you decided to do and why these emergency works are the most appropriate course of action.
Questions 4 and 5 are to be completed by the client, or the agent acting for them. Each question shows Answered or Needs answer. The answers fill in the later forms for you: the Responsible Person's name and organisation go to the ER01 sign-off, the approval step, ER02 and ER03.
5. Building Info
The building's details come from the building itself and are locked here: name, address and location. Open the building to change them.
- HRB reference: if the building doesn't have it yet, enter it here. It is saved to the building too, so it is there next time.
- Building documents: choose them from the building's documents or upload them: block plan, general arrangement, roof plan, ground floor, elevations, structural drawings and others. The block plan and the general arrangement are required for the package.
6. Asset Tag
What the works are about and where.
- Add asset tag: pick the tag from the building's asset register, or create one if the building has none. For each asset, give the asset tag and the description of works (scope).
- Pin the works location on the floor plan: choose the pin tool, click the plan, and drag the pin to the exact spot. Each asset gets its own pin. If the building has no plan yet, upload one (PDF, PNG or JPG); it becomes the building's plan.
Assets you add here show on the building as provisional until the record reaches Package ready. At least one asset is required for the package.
7. Worker Details
Who carried out the works: name, employer and email, entered by hand, and their digital signature, drawn on screen or uploaded as an image. A new signature replaces the old one, which stays in the record's history. All four are required for the package.
8. ER01 Contractor Risk Assessment
The Emergency Works Notification (Regulation 10). The project and building details are filled in for you. Complete each section; each one shows Needs input or Completed:
- Description of works: what is being done, where and how.
- Reason for urgency: the emergency criteria, the imminent risk, why the normal route isn't viable, and the timeframe.
- The risk to the health, safety and welfare of people in or about the building.
- Why it isn't possible to apply for building control approval.
- Whether you have exhausted all other options.
Sign-off (Responsible Person): name, position, organisation and date, filled in from the Client Assessment, and a digital signature. The sign-off name, date and signature are required for the package.
9. Materials & Photos
For each asset:
- Materials used: name, quantity and unit.
- Photos in three stages: Before, During and After. Drop photos onto a stage, or press + to upload.
The package needs at least one photo of each stage. In the package, photos are filed by asset tag and stage.
10. RP approves
The Responsible Person reviews the notification and confirms it. They see a summary (building, works, start date and competent person), then:
- tick I confirm the information above is accurate and that works are being carried out in compliance with the Building Safety Act;
- give their name and role;
- sign.
Their approval is a legal requirement before the notification to the BSR. Questions or requested changes go in the Comments thread, which is kept on the record. The confirmation, name and signature are required for the package.
11. ER02 – Client Signed Statement
Only needed when an agent acts for the client. If the record has no agent, the step says so and you can skip it.
Fill in the building name and location (its address, or easting and northing if it has none), the agent organisation (name and address), and the client authorisation: the client organisation's name and address, who signs, the date, and the signature. Most of it is filled in from the record.
When the form is complete, Core generates the ER02 PDF in the BSR's layout, and regenerates it whenever an answer changes. It is kept on the record and goes into the package. The BSR's instructions on the form say to send it to [email protected].
12. Package ready
Core lists everything still outstanding: the Work Record Setup, the five questions, the building documents, assets, photos of each stage, the worker, the ER01 sign-off, the Responsible Person's approval, and ER02 and ER03 when they apply. Click an item to open its step, or Ignore it if the package has to go without it (ignored items can be restored).
- Download package is available once nothing is outstanding.
- Download anyway (N missing) downloads it as it is.
- Share with externals gives someone outside your organisation access to the record.
The package holds the record's status report, the building documents, the photos by asset and stage, the worker's signature, and the ER02 and ER03 PDFs. See The package and the golden thread.
13. ER03 – Regularisation Application
Required when the works had already started (question 1). It is the BSR's Regulation 47 application:
- Application name and building name.
- Statement, with name, date and signature.
- Applicant details: client or agent, name, telephone, email, organisation type, name and address.
- Building name and location.
- Description of the work undertaken, and the dates the work commenced and completed.
When it is complete, Core generates the ER03 PDF in the BSR's layout. It goes into the package. The form explains that no drawings are needed up front (the BSR asks for them), that a Client Signed Statement is needed if an agent applies, and that BSR charges apply.
Because ER03 asks for the completion date, it usually comes after the first download of the package: download it again once ER03 is done.
14. Communications
Two conversations:
- General: questions, updates, confirmations and documents exchanged about the record.
- Additional remedial work required by the BSR: when the BSR rejects the works or asks for more, keep its decision, the remedial work and your response here, so the record shows what was asked and what was done.
15. Golden thread
Everything the record holds and who did what along the way. The audit trail is append-only. Submit sends the record.